The area behind the Easton Public Market (at Fourth & Church Streets) is currently under construction as the City of Easton makes way for a brand new parking garage! We’re looking forward to expanded parking options and a welcoming new pedestrian plaza right outside our doors. In the meantime, please excuse our appearance. We appreciate your patience and highly recommend that you  use the Pine Street parking garage which is a short one block walk down the quaint Bank Street Alley (did we mention that you’l pass Bank Street Creamery along the way?). More parking info

Construction Update: 1-4-22

The crane for the parking deck construction project will be arriving on 1/11/22 and will have N. 4th St. closed from Northampton St. to Spring Garden St. for all of 1/11 and half of 1/12. – Additionally, while the crane is operating (during business hours of 7 am – 4 pm on weekdays) N. 4th St. will become 1 way NORTH from Northampton St. to Spring Garden St. Outside of those times N 4th St. will remain 2 ways.

– This phase of the project is expected to take 12 – 13 weeks and will involve assembling over 450 sections of the parking garage structure. As they approach the last sections to be assembled (the last two weeks) the crane will be operating on N. 4th St and it will be closed for that period of time. We’ll be sure to keep you all updated as things progress, the expected completion date is June 30th, 2022.